case study 1
- Local High School needed a deck installed out over a pond for a future outdoor classroom.
- Innovative Pier Solutions installed 4 Helical Piers at a depth of 14′ and a torque rating that will hold 20,000 pounds per pier.
- We capped off the piers with a custom-made cap where the customer can run double 2 x 12 and be ready to build the future deck immediately.
- Even in a pond we can drill down for a deck support and have the customer ready to build that deck in a day.
- No mess, no concrete and guaranteed support for the deck.
case study 2
- Customer had a difficult site in the woods but wanted a utility shed out of site.
- Minimal access to site, no problem for Innovative Piers
- Achieved desired torque within 14 Ft.
- Installed 4 Helical Piers with Saddle Brackets placed on top of Helical Pier
- Immediately ready for shed to be placed
- Quick, easy and ready to go within 3 hours of arriving on site.
case study 3
- Customer was concerned that the sonotube that was placed would settle over time and not support the steel beam walkway from the main house to the dune.
- Innovative Pier solutions was contacted to access load bearing and find a solution to enhance the existing sonotube to insure that it would support the steel beam walkway.
- We installed a 8″- 10″-12″ Helix Pier next to the existing sonotube.
- We drilled the Helix down 14′ – 21′ to achieve a desired torque rating to help partially bear the weight of the walkway.
- We then put a new construction cap on top of the pier.
- We drilled reinforcing rod with epoxy into existing sonotube.
- Our Helical Pier was directly under the reinforced rod cage.
- We added a new sonotube on the side of existing and filled it with concrete to help redistribute partial weight of the walkway to our Helical Pier.
- Customer was able to rest assured that settling would not be an issue for the walkway and continue construction.
case study 4
-
Customer wanted to build multiple cabins in the woods for a local campground.
-
The site would be a challenge for any other type of foundation.
-
Installing Helical Piers was a logical option.
-
They contacted Innovative Piers with specific specs and bearing loads that were needed.
-
They accepted our bid and we proceeded to order the piers and get them scheduled.
-
We installed 11 piers per building at a determined elevation that was set by the builder.
-
All piers were installed per the required loads that were needed for bearing.
-
No excavation /soil disruption was needed and we were able to install 3 buildings with 11 piers each in one day.
-
We installed an 8 X 8 New Construction cap on top of our piers so they would be able to set their steel beams directly on top.
-
The customer was able to start construction of the cabins the next day.
-
We were able to give the customer a discount for doing multiple cabins at one time.
-
Contact Innovative Pier Solutions for any type of job.
case study 5
-
Customer had a difficult site overlooking a small creek where he wanted to add on to an existing deck.
-
The ground was quite spongy and unable to bear the weight of the deck building it in a standard way.
-
They contacted Innovative Pier Solutions to meet and determine a solution.
-
We decided to install 8″ X 10″ Helix Leads to a depth needed to achieve the required torque.
-
The Majority of the 13 Piers that were needed had to go to a depth of 14′ to achieve the needed torque.
-
We capped off the piers with a custom saddle bracket to accommodate the posts he needed.
-
All Piers were installed in less than one day and were immediately loadable.
-
Builder was able to start installing the deck the next day.
-
Eco Friendly installation with no excavating or concrete needed.
-
Contact Innovative Pier Solutions for your next deck project where you are dealing with either a tough location, poor soil or just want a quicker non – invasive install.
case study 6
-
Customer Contacted Innovative Piers in need of support for a Pergola in the backyard:
-
It was a very tight sight with limited access.
-
It had to be installed in an existing patio to eliminate having to tear up the patio.
-
It had to be installed to a depth that would support the Perola Structure.
-
Helical Piers were the perfect option with the existing conditions.
-
Two circular holes were drilled in the patio in order to install the piers.
-
Innovative Piers installed Two Helical Piers with 8″ X 10″ leads.
-
Required torque was achieved at 14 ft.
-
Drilling the piers we had very little torque until we reached the 12 ft. mark. Digging down and installing a concrete pier would not be practical because of the depth and the location of the piers that were needed to support the Pergola.
-
The builder was planning on pouring on top of our pier so we installed a 6″ X 6″ flat cap for support.
-
Innovative Pier Solutions arrived on site, installed the piers and left very little yard damage, all within 3 hours.
-
The piers were immediately loadable and eco friendly.Contact Innovative Pier Solutions for your next project.
case study 7
- Customer contacted Innovative Piers for a lakefront home that they wanted to add an addition too.
- Jobsite was tight with limited access.
- The Builder could not dig down for a typical concrete frost wall due to water level.
- The Builder also wanted an eco-friendly solution without having to dig down, pump out water and pour a concrete column.
- Builder contacted Innovative Piers to install Helical Piers for support. They told us the weight of the addition so we could install our piers to the proper torque.
- We installed 4 Helical Piers with saddle brackets.
- The Piers were immediately loadable and very little yard damage was done.
- Total time on the jobsite was 3 hours.
- Fast and efficient solution to a lakeside project.
- Contact Innovative Pier Solutions!
case study 8
-
Customer wanted to install a covered porch in his backyard without excavation, and without messing up his yard.
-
Innovative Pier Solutions used it’s new machine for installing in small tight conditions.
-
The Customer gave us the working loads needed and we installed 2 Helical Piers to a torque of 3,500 which would easily handle the weight of the project.
-
No Excavation was needed and we installed them without tearing up the backyard.
-
The Builder gave us the location and the elevation needed for installation.
-
Innovative Pier Solutions installed them in a couple of hours and they were immediately ready to build on.
-
Contact Innovative Pier Solutions for your project.
-
Big or Small, We do it all!!!